| | | | | | | | City of Davenport Agenda Group:
Department: Public Works Committee
Contact Info: Eric Gravert; (563) 327-5125
Wards: 1 & 4 | Action / Date 1/4/2017 |
Subject: Motion accepting the Birchwood Area Parallel Sewer Project completed by Valley Construction of Rock Island, IL. This project was satisfactorily completed with a final contract amount of $1,215,000 budgeted in CIP #01905. [Wards 1 & 4] |
|
| | | | | | | | Recommendation: Approve the motion. |
|
| | | | | | | | Relationship to Goals: Upgraded City Infrastructure |
|
| | | | | | | | Background:
To increase sewer capacity to the Birchwood Area a 15" parallel relief sewer was constructed on Clark Street from Locust Street to West Central Park Avenue.
This project was satisfactorily completed with a final contract amount of $1,215,000 budgeted in CIP #01905. |
|
|