Item Coversheet

City of Davenport

Department:  Public Works - Admin
Contact Info:  Zach Peterson | 563-328-6709
Action / Date
4/28/2021
Subject:

Motion awarding the scope of services for the River Heritage Park Safety Railing Removal and Resetting project to Crawford Company of Rock Island, Illinois in the amount of $55,147, CIP #68013. [Ward 3]

Recommendation:

Pass the Motion.

Background:

The City of Davenport is undertaking the structural repair of the government seawall at River Heritage Park. As part of this project, the existing safety railing will be dismantled, re-finished, and reset into the repaired wall.

 

Crawford Company, as the original fabricator of the railing, has been named as a sole source provider of the railing and will be working with the seawall repair contractor to ensure the successful dismantling and resetting of the railing panels into the repaired wall.

 

As part of this construction scope, Crawford Company will execute the following:

 

Re-Coating of Original Panels:

 

  • Provide the labor to pick up the existing extracted railing and posts from the site.
  • Sweep blast assemblies to remove any loose powder coating materials.
  • Recoat assemblies black, and bake to ensure proper adhesion.
  • Deliver assemblies back to the project site once completed.

Scope Price: $19,485

 

Panel Re-Installation:

 

  • Provide the materials and fabrication of steel retaining braces for supporting the wall.
  • Provide the lumber, stakes and hardware for the temporary bracing of this railing to be set in position before the new wall cap has been poured.
  • Provide the labor and equipment to set the railing segments in position. We will then pull off the site while your civil contractor pours the new concrete wall cap.
  • Remove of bracing and site cleanup of these materials.

Scope Price: $35,662

 

The above outlined improvements are being scheduled for late spring 2021 construction bid with substantial completion estimated to occur in early summer 2021.

 

The total project cost under this project scope is $55,147.