Background:
Public Works has revised the
previous alley program to better align the process with the construction season
and to provide incentive for additional participation. The process now begins
alley reconstruction/resurfacing requests by receiving a petition signed by 30%
of the property owners on the block face. Staff will then provide cost
estimates based on the following updated cost sharing:
Residential - 25% property
owner/ 75% City funds
Commercial - 50% property
owner/ 50% City funds
If over 50% of the property owners
wish to ‘opt out’ of the program, then the alley does not move forward in the
assessment process. This ‘opt out’ period has occurred and the following
alleys have been identified to participate in the reconstruction program:
- The north-south
residential alley from East Rusholme Street to East Denison Avenue between
Brady Street and Pershing Avenue.
- The north-south
residential alley from East 17th Street to East 18th Street between Perry
Street and Pershing Avenue.
- The east-west
commercial alley from Western Avenue to Scott Street between West
3rd Street and West 4th Street.
- The north-south
commercial alley from East 4th Street to East 5th Street between
Brady Street and Perry Street.
- The north-south
commercial alley from West 4th Street to alley end between Harrison
Street and Main Street.
The total estimated cost of these improvements
is $300,000.